12. Design of the Replacement of the Woodrow Wilson Memorial Bridge 8:45 9:10
Robert Healy, Maryland State Highway Administration
Sean Bluni, Hardesty & Hanover, Greg Shafer, Parsons
13. Movable Bridge Pier Protection and W. Bridge Fender System Design 9:10 9:35
Dayi Wang, P.E., Gaurav Mathur, Jacobs Civil Inc
14. Innovative Design Concepts for Bostons New Chelsea Street Bridge 9:35 10:00
Anthony L. Bartello, Eric T. Kelly, HNTB Corporation
15. Construction Repairs to the Bascule Span of the Tacony-Palmyra Bridge10:30 -10.50
Matthew Colon, John Q. Wong, DMJM&HARRIS
16. Methods, Effects and Implications of Bascule Balancing 10:5011:10
Thomas Cherukara, FDOT
17. Asset Management of Movable Bridges in Florida 11:1011:30
Alan Klevens, Steven A. Shaup, Lichtenstein Consulting Engineers, Inc.
Seta Koroitamudu, FDOT, Timothy Howell, VMS Maintenance Systems, Inc.
18. Main Counterweight Ropes Replacement-Burlington Canal Lift Bridge 11:3011:50
David O. Nyarko, Parsons Brinckerhoff
19. Spuyten Duyvil Emergency Response to Navigation Strikes 1:30 1:50
Craig J. Rolwood, Hardesty & Hanover, LLP
Alex Ostrovsky, Amtrak
20. Emergency Repairs to Willow Street Lift Bridge 1:50 2:10
Richard Stein, City of Cleveland
21. Computerized Simulation Optimizes Hydraulic Drive System Design 2:10 2:30
Janine Krempa, Bosch Rexroth Corporation
22. Construction and machining tolerances for rolling leaf bascule 2:30 2:50
Harry Roecker, DMJM&HARRIS
Adjourn 4:00